Progress highlights – June July 2023

White

Highlights from the New Medical Facility Project Team’s July meeting

Detailed design approved

The detailed design for our new medical facility project was signed off by the Board on 20 July 2023. 

Design documentation finalisation

The Design documentation which will serve as the basis for the tender documentation – is now being finalised by the architects, Billard Leece Partnership and Workshop Architecture.

Current stage – Tender preparation

The BDAC Infrastructure team is now preparing the tender documentation and the associated contract terms and conditions. The tender will soon be issued to selected construction companies.

Probity Advisor appointed

As this project is of significant scale, AFS Accountants have been appointed as our probity auditors to ensure transparency and accountability in all aspects of the procurement of the construction company/ builder to the project. 

Ensuring Community involvement

In addition to ensuring the probity of the project, BDAC is also incorporating guidelines into the tender to ensure that the project benefits the local Aboriginal Community during the construction. Our procurement process reflects BDAC’s values and prioritises the use of local and Aboriginal employees, trainees, contractors and suppliers wherever feasible. If you are a tradesperson from Community, or know of someone looking for a traineeship, let us know.

If you would like to be kept informed or get involved in community engagement opportunities, please sign up to our newsletter to have these opportunities and progress updates sent to your inbox: